Project maturity and risk

A multidimensional view of the gates between an announcement and an executable project: resource, studies, capital, permits, power, infrastructure, construction, market and delivery capability.

NO AGGREGATE SCORE

An average would hide critical gates. Each cell therefore preserves its maturity, risk, evidence and assessment date. One weak dimension can block the entire project.

METHOD

Statuses describe only what public sources establish as of the stated date. They are not an investment recommendation, authorization or construction forecast.

MATURITYAdvancedPartialEarlyNot evidenced
RISKLowMediumHighUnknown
Comparative matrix of projects tracked by Québec2035
PROJECTRESOURCESTUDYCAPEXFINANCINGPERMITSENERGYINFRASTRUCTURECONSTRUCTIONMARKET / OFFTAKEEXECUTION
Matawinie Mine

Final investment decision and construction announced; risk shifts to delivery.

ASSESSED 2026-08-07
AdvancedRisk: Low

Documented mineral base.

AdvancedRisk: Low

Advanced project studies.

AdvancedRisk: Medium

Construction budget established; inflation remains a watch item.

AdvancedRisk: Low

FID and financing announced in May 2026.

AdvancedRisk: Low

Authorizations supporting the represented start.

PartialRisk: Medium

Power integrated into plan, delivery to monitor.

PartialRisk: Medium

Access and facilities under delivery.

PartialRisk: Medium
GATE

Construction launched, not completed.

AdvancedRisk: Medium

Customers and integrated chain identified; performance still to deliver.

PartialRisk: Medium
GATE

The main test is now cost, schedule and commissioning.

Anode Material Plant (Bécancour)

Strategic downstream asset, but dependent on financing, grid and sequencing with Matawinie.

ASSESSED 2026-08-07
Not applicableRisk: Not applicable

Processing plant; feedstock addressed under market/offtake.

PartialRisk: Medium

Engineering advanced, delivery still to confirm.

PartialRisk: Medium

Capital need defined in the integrated plan.

PartialRisk: High
GATE

The complete downstream financing package remains a gate.

PartialRisk: Medium

Site permits to track through full start.

PartialRisk: High
GATE

Bécancour grid reinforcement is required.

PartialRisk: Medium

Industrial platform exists, connections must be delivered.

EarlyRisk: High
GATE

Full construction is not represented as launched.

AdvancedRisk: Medium

Integrated customer chain announced; delivery conditions to confirm.

EarlyRisk: High
GATE

High dependency on mine-plant-grid sequencing.

Troilus Project

Advanced feasibility and positive power signal; permits, financing and start remain open.

ASSESSED 2026-08-07
AdvancedRisk: Low

Resource and reserve integrated into feasibility.

AdvancedRisk: Low

2024 NI 43-101 feasibility study.

AdvancedRisk: Medium

C$1.075B initial capex estimated, not financed.

EarlyRisk: High
GATE

Construction financing not demonstrated.

PartialRisk: High
GATE

Environmental assessment is ongoing.

PartialRisk: Medium

70 MW allocation announced by the proponent.

PartialRisk: Medium

Northern access and connections must be executed.

Not evidencedRisk: High
GATE

No confirmed construction start.

EarlyRisk: High
GATE

Binding offtake not demonstrated in tracked sources.

EarlyRisk: High

Permitting-to-financing-to-execution transition remains.

Dumont Nickel Project

Large technical base, but financing, offtake and execution update condition the project.

ASSESSED 2026-08-07
AdvancedRisk: Low

Large reserve documented in the 2019 report.

AdvancedRisk: Medium

Complete feasibility, but 2019 baseline needs updating.

AdvancedRisk: Medium

Historically defined capex; update required.

PartialRisk: High
GATE

Financing package still explicitly sought in 2026.

AdvancedRisk: Medium

Authorization history; conditions and updates must be maintained.

PartialRisk: High
GATE

Connection and power capacity remain critical path.

PartialRisk: Medium

Road and rail nearby; project-specific works must be delivered.

Not evidencedRisk: High
GATE

Construction targeted, but not confirmed as started.

PartialRisk: High
GATE

Guaranteed concentrate agreements remain a 2026 objective.

EarlyRisk: High
GATE

Detailed engineering and construction decision remain.

Horne 5 Project

Advanced 2026 feasibility; authorization, capital and start are not secured.

ASSESSED 2026-08-07
AdvancedRisk: Low

Mineral base integrated into 2026 feasibility.

AdvancedRisk: Low

Feasibility study updated in 2026.

AdvancedRisk: Medium

Pre-production capex estimated at C$1.75B.

EarlyRisk: High
GATE

Construction financing not confirmed.

PartialRisk: High
GATE

MELCCFP/BAPE file in process; no decree represented.

PartialRisk: Medium

Needs and connection to confirm in execution path.

PartialRisk: Medium

Complex urban project with existing interfaces.

Not evidencedRisk: High
GATE

No confirmed construction start.

PartialRisk: Medium

Marketable metals, but project commercial arrangements to confirm.

EarlyRisk: High
GATE

Permits, financing and urban interfaces dominate risk.

Bégin-Lamarche Project

Resource and PEA established; feasibility, permits, infrastructure and firm sales remain decisive.

ASSESSED 2026-08-11
AdvancedRisk: Medium

2026 measured, indicated and inferred resource; not a reserve.

PartialRisk: High
GATE

PEA published; feasibility and engineering funded but not completed.

PartialRisk: High

C$675M in the 2024 PEA; estimate requires refinement.

EarlyRisk: High
GATE

C$16.7M development support, not construction financing.

EarlyRisk: High
GATE

Full permitting path not demonstrated as complete.

PartialRisk: Medium

Nearby line per proponent; firm connection must be demonstrated.

PartialRisk: High
GATE

Power-connection and road-access studies are funded; routes, authorizations and construction remain outstanding.

Not evidencedRisk: High

No confirmed mine construction.

PartialRisk: High
GATE

Letter of intent and limited prepayment; firm contract must be demonstrated.

EarlyRisk: High

Multiple gates must converge before investment decision.

Port of Baie-Comeau Terminal 5

Clear port need and public information period completed; authorization, full scope and tenders remain open.

ASSESSED 2026-08-11
Not applicableRisk: Not applicable

Infrastructure project without a mineral resource.

AdvancedRisk: Medium

Impact study deemed acceptable; detailed design remains projected.

PartialRisk: High

C$56M for a scope excluding several related works.

PartialRisk: High
GATE

Complete financing plan not demonstrated in tracked file.

PartialRisk: High
GATE

Public information period ended August 7, 2026; no government authorization is represented.

Not applicableRisk: Not applicable

Not identified as a primary gate in the public scope.

PartialRisk: High

Core wharf defined; warehouse, rail and access sit outside costed scope.

Not evidencedRisk: High
GATE

2027 tenders and construction are projections.

PartialRisk: Medium
GATE

Multi-user demand targeted; firm commitments not published.

EarlyRisk: High
GATE

Authorization, design, procurement and interfaces must sequence.

PPAW2 Wind Farm

Contract and configuration defined; BAPE hearing and authorization still precede construction.

ASSESSED 2026-08-11
Not applicableRisk: Not applicable

Wind generation project.

AdvancedRisk: Medium

Impact study and public documentation available.

PartialRisk: Medium

Approximately C$1B announced; estimate must be secured.

PartialRisk: Medium

Partnership and contract support the file; full close not demonstrated.

PartialRisk: High
GATE

BAPE hearing underway; no final authorization represented.

AdvancedRisk: Medium

Generation and contracted capacity defined.

PartialRisk: High
GATE

Collector system, roads and grid connection remain to deliver.

Not evidencedRisk: High
GATE

2027 start targeted, not confirmed.

AdvancedRisk: Low

291.4 MW contracted capacity in BAPE file.

EarlyRisk: High
GATE

Permits, acceptance, procurement and schedule remain critical.

Crater Lake Project

Distinctive resource, but pre-feasibility, access, energy and binding market remain at demonstration stage.

ASSESSED 2026-08-11
AdvancedRisk: Medium

2025 indicated and inferred resources; not reserves.

EarlyRisk: High
GATE

Pre-feasibility commissioned; final result not yet integrated.

Not evidencedRisk: High

Robust project capex not published in tracked sources.

EarlyRisk: High
GATE

C$6.9M for technical development, not construction financing.

EarlyRisk: High
GATE

Full regulatory path must be established.

EarlyRisk: High
GATE

Site generation and regional options require study.

EarlyRisk: High
GATE

Current air access; road outside pre-feasibility per proponent.

Not evidencedRisk: High

No confirmed construction.

EarlyRisk: High
GATE

Alloy work underway, without demonstrated binding offtake.

EarlyRisk: High

Project must convert the resource into an integrated, financeable plan.